Hi all,
On some reports, the 'Schedule' radio button is grayed out. The documentation states that 'If the Schedule radio button is grayed out on the report / utility window, scheduling is not currently enabled for the selected report.'
Can scheduling be enabled for some of these reports? If so, is it a difficult thing to do? (Note that I'm not the DBA here ... just making more work for him!)
Thanks!
Paul
Wow, that was easy – thanks, Ryan!
From: Tessitura Technical Forum [mailto:forums-technical@tessituranetwork.com] On Behalf Of Ryan CrepsSent: Wednesday, February 23, 2011 11:42 AMTo: Paul GoetzSubject: RE: [Tessitura Technical Forum] scheduling reports
Check in Tessitura Report Setup that the “Allow Schedule” checkbox is ticked for the particular report you are noting here.
-Ryan
From: Tessitura Technical Forum [mailto:forums-technical@tessituranetwork.com] On Behalf Of Paul GoetzSent: Wednesday, February 23, 2011 2:32 PMTo: Ryan CrepsSubject: [Tessitura Technical Forum] scheduling reports
This message was sent automatically to you by www.tessituranetwork.com because you subscribed to the Tessitura Technical Forum. You may reply to this message to post to the Technical forum or visit the site to search, read and post to the forums. In the interest of keeping the forum posts from becoming cluttered, we encourage you to delete previous message text from your reply before sending. Thank you!