Hi all,

 

This is probably a daft question, but my morning coffee hasn’t had time to kick in yet!  Yesterday, I’d deleted two emails from a daily sales report schedule, but this morning, those two emails still received the report.  Have I missed a trick, or just a blindingly obvious ‘this is the way it always works’?

 

Cheers,

Kathleen

 

 

The first Made In Northampton play of the Autumn season, the darkly compellingThe Talented Mr Ripley, continues in the Royal auditorium until Sat 9 October. Over in the Derngate auditorium the hilarious musical Spamalot takes over the stage from Mon 27 September to Sat 2 October, starring Marcus Brigstocke, Hayley Tamaddon and Todd Carty. Visit www.royalandderngate.co.uk for more details and to book tickets.

 

Book your tickets now by calling 01604 624811 or visit www.royalandderngate.co.uk

 

The Northampton Theatres Trust Ltd. Registered in England and Wales. Company Registration No. 3640915. Registered Office: Royal & Derngate, Guildhall Road, Northampton NN1 1DP

 

Royal & DerngateMission

Parents
  • Kathleen,
     
    Changes apply on the next report run.
     
    Sabina Spilkin
    San Diego Symphony
    619.615.3904

     


    From: Tessitura Technical Forum [mailto:forums-technical@tessituranetwork.com] On Behalf Of Gary Halliday
    Sent: Wednesday, September 29, 2010 5:57 AM
    To: Sabina Spilkin
    Subject: RE: [Tessitura Technical Forum] change to report schedule not taking effect

    Hi Kathleen,

     

    When you amend a report schedule your changes only apply after the next report has run, I’m sure I have read about this changing somewhere but I might be making that up.

     

    Gary

     

    From: Tessitura Technical Forum [mailto:forums-technical@tessituranetwork.com] On Behalf Of Kathleen Smith
    Sent: 29 September 2010 10:22
    To: Halliday, Gary
    Subject: [Tessitura Technical Forum] change to report schedule not taking effect

     

    Hi all,

     

    This is probably a daft question, but my morning coffee hasn’t had time to kick in yet!  Yesterday, I’d deleted two emails from a daily sales report schedule, but this morning, those two emails still received the report.  Have I missed a trick, or just a blindingly obvious ‘this is the way it always works’?

     

    Cheers,

    Kathleen

     

     

    The first Made In Northampton play of the Autumn season, the darkly compellingThe Talented Mr Ripley, continues in the Royal auditorium until Sat 9 October. Over in the Derngate auditorium the hilarious musical Spamalot takes over the stage from Mon 27 September to Sat 2 October, starring Marcus Brigstocke, Hayley Tamaddon and Todd Carty. Visit www.royalandderngate.co.uk for more details and to book tickets.

     

    Book your tickets now by calling 01604 624811 or visit www.royalandderngate.co.uk

     

    The Northampton Theatres Trust Ltd. Registered in England and Wales. Company Registration No. 3640915. Registered Office: Royal & Derngate, Guildhall Road, Northampton NN1 1DP

     

    Image removed by sender. Royal & DerngateImage removed by sender. Mission




    This message was sent automatically to you by www.tessituranetwork.com because you subscribed to the Tessitura Technical Forum. You may reply to this message to post to the Technical forum or visit the site to search, read and post to the forums. In the interest of keeping the forum posts from becoming cluttered, we encourage you to delete previous message text from your reply before sending. Thank you!


    www.southbankcentre.co.uk

    Ticket Office: 0844 847 9910

    Southbank Centre is a Registered Charity No. 298909

    ______________________________________________________________________

    This message (and files transmitted with it) may contain confidential or copyright information. If you receive it in error, please notify the sender and delete it from your computer.

    _______________________________________________________________________



    This message was sent automatically to you by www.tessituranetwork.com because you subscribed to the Tessitura Technical Forum. You may reply to this message to post to the Technical forum or visit the site to search, read and post to the forums. In the interest of keeping the forum posts from becoming cluttered, we encourage you to delete previous message text from your reply before sending. Thank you!
Reply
  • Kathleen,
     
    Changes apply on the next report run.
     
    Sabina Spilkin
    San Diego Symphony
    619.615.3904

     


    From: Tessitura Technical Forum [mailto:forums-technical@tessituranetwork.com] On Behalf Of Gary Halliday
    Sent: Wednesday, September 29, 2010 5:57 AM
    To: Sabina Spilkin
    Subject: RE: [Tessitura Technical Forum] change to report schedule not taking effect

    Hi Kathleen,

     

    When you amend a report schedule your changes only apply after the next report has run, I’m sure I have read about this changing somewhere but I might be making that up.

     

    Gary

     

    From: Tessitura Technical Forum [mailto:forums-technical@tessituranetwork.com] On Behalf Of Kathleen Smith
    Sent: 29 September 2010 10:22
    To: Halliday, Gary
    Subject: [Tessitura Technical Forum] change to report schedule not taking effect

     

    Hi all,

     

    This is probably a daft question, but my morning coffee hasn’t had time to kick in yet!  Yesterday, I’d deleted two emails from a daily sales report schedule, but this morning, those two emails still received the report.  Have I missed a trick, or just a blindingly obvious ‘this is the way it always works’?

     

    Cheers,

    Kathleen

     

     

    The first Made In Northampton play of the Autumn season, the darkly compellingThe Talented Mr Ripley, continues in the Royal auditorium until Sat 9 October. Over in the Derngate auditorium the hilarious musical Spamalot takes over the stage from Mon 27 September to Sat 2 October, starring Marcus Brigstocke, Hayley Tamaddon and Todd Carty. Visit www.royalandderngate.co.uk for more details and to book tickets.

     

    Book your tickets now by calling 01604 624811 or visit www.royalandderngate.co.uk

     

    The Northampton Theatres Trust Ltd. Registered in England and Wales. Company Registration No. 3640915. Registered Office: Royal & Derngate, Guildhall Road, Northampton NN1 1DP

     

    Image removed by sender. Royal & DerngateImage removed by sender. Mission




    This message was sent automatically to you by www.tessituranetwork.com because you subscribed to the Tessitura Technical Forum. You may reply to this message to post to the Technical forum or visit the site to search, read and post to the forums. In the interest of keeping the forum posts from becoming cluttered, we encourage you to delete previous message text from your reply before sending. Thank you!


    www.southbankcentre.co.uk

    Ticket Office: 0844 847 9910

    Southbank Centre is a Registered Charity No. 298909

    ______________________________________________________________________

    This message (and files transmitted with it) may contain confidential or copyright information. If you receive it in error, please notify the sender and delete it from your computer.

    _______________________________________________________________________



    This message was sent automatically to you by www.tessituranetwork.com because you subscribed to the Tessitura Technical Forum. You may reply to this message to post to the Technical forum or visit the site to search, read and post to the forums. In the interest of keeping the forum posts from becoming cluttered, we encourage you to delete previous message text from your reply before sending. Thank you!
Children
  • It looks like you are experiencing a similar issue to what I am experiencing.  We modified the job and on the subsequent run, the prior Output Option appears to be the same.

    We have a job that runs every night and has been scheduled to run every night since the beginning of the season.  It was set to run every morning and the output option was set to “Data Center”.  It was set to this option because we had difficulty getting the e-mailing PDF files to function.  We finally got the e-mailing PDF files resolved and scheduled a similar job to run every morning with the “Email-PDF” as the output option and it worked great.  We went into the “Maintain Report/utility schedule” and edited the output option to be the desired “Email-PDF” and saved it.  When  the job is opened again, it displays the “Email-PDF” in the Output option field. 

    The fix for the e-mail issue was that the server was not able to create PDF files because the folders under the PBVM folder had a bad set of GS driver files.  When we got a clean copy of these subfolders from a working system, everything functioned as designed and desired.

    The problem is that when the job runs, it does not e-mail the PDF, but a similar job that was created initially with the correct Output Option emails perfectly.  Does anyone know why the job that was edited still acts like “Data Center” is selected as the Output Option instead of the “Email-PDF”?  I examined all logs and did not find any errors during the run of this job.  And like I said earlier, the same report being run with a different season selected as the only difference between the runs does e-mail properly.

     

    Thanks in advance.

    Allen Clark,

    Manager of Information Systems