We hadn't built our "First Friday" Production Season for FY24 until yesterday, not realizing that our teammate had already input all of her First Friday events for the rest of the year using the FY23 First Friday Production Season (our FY starts July 1, so some of them went into the wrong FY Production Season). Oops!
Is there a way to move all of them (there are at least 6 performances that need to get switched) into the correct Production Season? We really don't want to have to delete and re-build everything if it's avoidable.
You can use the Reschedule button the performances to open the rescheduling window, and you can select a different production season. (Unlike the name implies, you don't need to change the date or time of the performance if you don't want to.)
Well, that's too easy of a way. lol.
Well that worked! lol
I just wish there was an easy way to do all of them all at once instead of using the reschedule button on every single performance. Season Maintenance is great for everything else, but rescheduling in mass isn't an option.
And here I am just happy that there is an application based solution to this. I have been using my own custom solution for this for years.
Sounds a little like a be careful what you wish for, taking into consideration what could go wrong along with what could go right. Like, if they make it, make sure it displays changes before you commit.
Fair enough. But I have also been using my own custom solutions to too many things at this point to look back. I will train new staff members with the proper methods. But I have become nearly untrainable at this point. Much as I even teach the opposite to others.
I meant that for wishing for mass updates in out of the box Tessitura, John. Sorry I replied to the wrong link in the chain. I, too, am untrainable.